The City of Ottawa invites you to review and provide comments on the new documents and illustrations for the Windsor Park Pumping Station Reliability Upgrades project by February 22, 2023. Your feedback can be submitted by email or by phone to the contact below.
What: Update features at the Windsor Park Pumping Station by upgrading various process components and the motor control center as well as adding a new driveway access to the facility.
Why: Increase reliability, improve maintainability of the station and providing safety improvements.
Where: Windsor Park Pumping Station, located at 507 Riverdale Avenue.
When: The current project schedule is as follows:
- Construction is expected to start in March 2023
- Construction is expected to conclude in December 2023
For further information about this project and/or to submit comments on the project, please contact the City project manager:
Mohamed El-Sarji, P. Eng.
Senior Engineer, Infrastructure Projects
Design and Construction – Facilities
100 Constellation Drive, Ottawa, ON K2G 6J8
Tel.: 613-580-2424, ext. 22191